Tshwane says Njala–Waltloo load transfer is about 95% complete

Tshwane says Njala–Waltloo load transfer is about 95% complete, with remaining power restoration targeted for Sunday subject to testing and commissioning.

By EBNewsDaily ReporterLast updated:

Updated on 2 October 2026 with Tshwane’s 08:24 restoration bulletin.

The City of Tshwane says its Njala–Waltloo electricity load-transfer process is approximately 95% complete, with power restored to more areas and remaining restoration targeted for Sunday, subject to successful testing and commissioning.

In its Friday morning bulletin, the city said supply had returned to Heatherly, Mamelodi 1, 2 and 3, Mooikloof, Wapadrand, Lynnwood, Villieria and Highlands, and approximately half of the Willows supply area.

The 95% figure refers to the load-transfer process, not the proportion of customers restored. Technical teams were monitoring the transferred load to maintain network stability.

Sunday target depends on testing

Tshwane said testing of a 35 MVA transformer and newly installed switchgear and cables at the fire-damaged Waltloo substation had been completed. This had enabled restoration to Eersterust, Nellmapius and parts of Leeuwfontein.

Teams were targeting completion of remaining work within three days. Restoring the remaining affected areas by Sunday, 4 October, depends on successful testing and commissioning.

The city asked customers whose supply had returned to limit simultaneous use of high-load appliances, particularly at peak times, to reduce overload and trip risks. It promised another bulletin before 21:00 on Friday.

Earlier capacity constraints

In its Thursday evening statement, Tshwane said one Njala transformer had failed required tests and the remaining functioning unit could not meet full demand.

That statement described staged load transfers involving Njala, Rietvlei and Kwagga. Friday’s bulletin reports further progress; it does not say all affected properties have electricity.